Technical specification

How resin bound surfacing is properly laid.

The depths, aggregate grades, resin ratios, weather windows and cure times we work to on every job. If a quote you have been given does not state these numbers, ask why.

Laying depths

Depth by application

ApplicationFinished depthAggregate gradeNotes
Footpaths & garden paths15 mm1–3 mmPedestrian only. Minimum practical depth for a stable, permeable finish.
Domestic paths & patios18 mm2–5 mmOur standard for cars and light vans up to 3.5 t.
Patios & courtyards15–18 mm1–3 mm or 2–5 mmDepth follows the base type and any level constraints at thresholds.
Commercial / light HGV20–24 mm2–5 mm (occasionally 3–6 mm)Laid over a reinforced or thicker bituminous base, designed per traffic loading.

Rule of thumb: the finished depth should be at least three times the largest stone size. A 2–5 mm aggregate therefore cannot be laid below 15 mm.

Weather window

Temperature & moisture limits

Resin is a chemical cure, not a drying process. Scottish conditions mean the laying window matters more here than almost anywhere else in the UK — we will postpone a job rather than lay outside these limits.

Minimum air temperature

10 °C

and rising — we do not start below this.

Minimum surface temperature

5 °C

measured on the base, at least 3 °C above dew point.

Maximum working temperature

25 °C

above this the pot life shortens sharply; we work early morning.

Relative humidity

Below 80%

high humidity slows cure and can cloud the resin.

Rain

Dry for 24 h after

no laying in rain, and no rain forecast during the initial cure.

Base moisture content

Below 2.5%

the base must be visibly dry — no standing water or damp patches.

Practical season: in the west of Scotland that usually means March to early November. Winter installations are possible with a winter-grade hardener, tented working and a heated, dry base — we will tell you honestly if the conditions do not suit.

Materials

Resin & mix ratios

Resin system
Two-part UV-stable aliphatic polyurethane (clear, non-yellowing)
Standard mix
7.5 kg resin (Part A + Part B) to 125 kg kiln-dried aggregate
Mixing time
Minimum 2 minutes forced-action mixing until every stone is coated
Pot life
Approx. 20 minutes at 15 °C — less in warm weather, more in cold
Aggregate
Kiln-dried, washed, moisture content below 0.5%
Coverage
One 125 kg mix covers roughly 6.5 m² at 18 mm

Cure times

When you can use it

Touch dry2–4 hours
Foot traffic6–12 hours
Vehicle traffic24–48 hours
Full chemical cure5–7 days

Times quoted at 15 °C. Every 10 °C drop roughly doubles them; below 10 °C the cure may stall altogether.

Build-up

The full construction, layer by layer

1. Excavation

Dig out 150–200 mm for a domestic path or patio (more on soft or clay ground), to a firm, uniform formation. Existing tarmac or concrete in sound condition can be retained as the base.

2. Sub-base

100–150 mm of MOT Type 1, or clean 20 mm angular stone / Type 3 where full permeability and SuDS compliance is required. Compacted in layers of no more than 75 mm with a vibrating plate or roller.

3. Edge restraints

Concrete-haunched kerbs, block edging, aluminium or steel edging installed before the base course so the finished surface is fully contained.

4. Binder course

50–65 mm of open-graded porous asphalt for permeable builds, or 60 mm AC20 binder plus 20 mm AC6 surface course for standard builds. Concrete bases require expansion joints to be carried through and a minimum 28-day cure.

5. Falls & drainage

Impermeable bases are laid to a minimum 1:80 fall away from the building, with channel drainage at thresholds. Fully permeable builds discharge through the sub-base, subject to soil infiltration testing.

6. Priming

Fresh asphalt is left 7–14 days before priming. Concrete, damp-prone or non-porous bases get a dedicated primer or damp-proof membrane, applied and allowed to tack off before resin is laid.

7. Laying & trowelling

Mixed material is placed and screeded to the design depth, then hand-trowelled with a smoother tool and a little denatured alcohol to close the surface. Wet edges are kept live so joints disappear.

8. Cure & handover

The surface is barriered off, checked for depth and finish once cured, and handed over with an aftercare sheet and written guarantee.

Quality control

What goes wrong, and why

  • Laying below 5 °C surface temperature

    Resin never fully cures — soft, sticky or crumbling surface.

  • Damp base or aggregate

    Foaming, blistering and loss of bond between resin and stone.

  • Under-mixing

    Dry, unbound stone that ravels out within weeks.

  • Laying too thin over a rough base

    Telegraphing, cracking and premature failure.

  • Skipping edge restraints

    Edges break away as soon as a wheel runs over them.

Aftercare

Looking after the surface

  • ✓Keep off completely for the first 24 hours; no vehicles for 48 hours.
  • ✓No turning the steering wheel while stationary — it scuffs any resin surface.
  • ✓Brush or blow leaves off regularly and rinse with a hose; a pressure washer under 150 bar, fan tip, held 300 mm back is fine.
  • ✓Treat moss and algae twice a year with a proprietary resin-safe cleaner.
  • ✓Never use rock salt for ice — use a plastic shovel and grit-free de-icer.
  • ✓Keep the permeable surface clear of silt so infiltration rates stay high.